GUVNL Concludes 250 MW Solar Auction at Rs2.60/kWh
Mar 06, 2025
Gujarat Urja Vikas Nigam Limited (GUVNL) has successfully completed a 250 MW grid-connected solar PV auction, with a greenshoe option for an additional 250 MW. The winning tariff for all awarded capacity was Rs2.60 per kWh.
Winning Contracts Overview
- Avaada Energy won 100 MW at Rs2.60/kWh.
- SAEL Industries secured 100 MW at Rs2.60/kWh.
- Welspun Renewable Energy obtained 50 MW at Rs2.60/kWh.
Auction Details
- GUVNL issued the Request for Selection (RfS) in January 2024.
- The selection process involved competitive bidding followed by a reverse e-auction.
- Bidders could submit projects that were under construction, already commissioned, or newly planned anywhere in India.
- Minimum bid requirements:
- 50 MW for interstate-connected projects.
- 10 MW for State Transmission Utility (STU) connected projects.
- The greenshoe option allowed for capacity expansion by up to 250 MW if required.